The grid connection queue is now the real cost of the energy transition
Capital and turbines are no longer the bottleneck for new generation. Waiting years for a connection is, and developers and utilities need to plan around it.


Darren Koh and Kamran Sadeghi
Share

Photo:
Five years ago, the conversations we had with renewable developers were about the cost of capital, panel prices and the availability of turbines. Today they are mostly about the grid. In many markets, a solar farm or battery site that could be built in eighteen months waits four to seven years for a connection, and the queue is getting longer.
The numbers are large. In the United States, more than 2,000 gigawatts of generation and storage sit in interconnection queues, roughly twice the country’s installed capacity. In Great Britain the queue passed 700 gigawatts before reforms began to clear it. Across Southeast Asia, transmission plans lag the generation targets they are meant to support by several years.
For developers, a connection date is now worth more than almost any other project attribute. For utilities and industrial buyers, the queue determines how fast they can decarbonize and what they will pay for power in the meantime. Both need to treat it as a strategic constraint, not an administrative one.
Most of the queue will never be built
Historically, only 15 to 25 percent of projects that enter a connection queue reach commercial operation. Many were speculative applications filed to hold a place. This inflates the queue, slows the studies needed for everyone else, and makes it hard for grid operators to plan.
Reforms in several markets now require higher deposits, proof of land rights and firm milestones. They are starting to work. In one European market we follow closely, the reformed queue was 40 percent smaller within a year, and study times for the remaining projects fell by about a third.
For developers, the implication is that a large pipeline measured in queue positions is worth much less than it looks. Investors are beginning to value portfolios accordingly, and we expect the discount on early-stage projects without a firm connection date to widen.
Location is now a grid decision
The traditional way to site a renewable project was to find good wind or sun, available land and a supportive community, and then apply for a connection. Increasingly, the order needs to be reversed: start from where the grid has headroom, or will have it soon, and work back.
That favors developers who invest in grid analysis early. The best we have seen maintain their own models of network capacity by substation, track planned reinforcements, and are willing to accept a lower-yield site with a connection in two years over a better one with a connection in six.
It also changes the economics of co-location. A battery added to an existing solar site can often use the same connection, and a site with surplus import capacity at a closed industrial plant can be worth more than the plant itself.
Utilities should sell flexibility, not just capacity
For transmission and distribution utilities, the queue is partly a symptom of connection rules written for a different system. Most still offer firm connections sized for the worst hour of the year, which leaves most of the network’s capacity unused most of the time.
Flexible or non-firm connections let a project connect earlier on the condition that its output can be curtailed when the network is constrained. Projects connected this way typically lose 2 to 5 percent of annual output and gain several years of revenue. One distribution utility we worked with connected 1.8 gigawatts of new generation in three years this way, against 400 megawatts under its previous rules.
What large energy buyers should do
Industrial companies with decarbonization targets are often relying on new renewable supply that sits somewhere in these queues. Few have checked how realistic its timing is.
A power purchase agreement with a project that has no connection date is a hope, not a supply contract.
The practical steps are to review the connection status of every project in the procurement pipeline, weight contracted volumes by the probability of delivery, and consider on-site generation, storage and demand flexibility as a hedge. A company that assumes its 2030 power will be clean, and discovers in 2028 that half of it is still in a queue, will have few good options left.
Keep reading
Directors' briefing: overseeing AI without becoming the AI committee
board-ai-oversight-briefing
Event
Trevor Ofori and Patrick Hofer
A morning briefing in Zurich, also streamed online, for board members on the questions to ask about AI risk, regulation and return, and how to fit them into the board's calendar.
Software Pricing 2026: the move from seats to usage
software-pricing-2026
Report
Divya Raghavan and Darren Koh
A survey of 318 B2B software companies on how AI features are changing what they charge for, how customers respond, and which pricing models are holding up.
Separating a business cleanly: a roundtable on carve-outs
carve-outs-roundtable
Event
Kamran Sadeghi and Victor Amaral
A small morning session in London for executives preparing to sell or spin off a division, on stranded costs, transition services and keeping both businesses running.
What China-plus-one sourcing really costs consumer brands
china-plus-one-sourcing-costs
Article
Gabriela Quintero and Divya Raghavan
Moving production to a second country lowers tariff exposure but adds cost in places most business cases miss. Here is how to size it before committing.
Workforce planning in insurance: plan for skills, not headcount
workforce-planning-in-insurance
Article
Lucy Barlow
Insurers face a retirement wave in underwriting and claims just as automation changes the work. Planning by headcount misses both. Planning by skill family does not.
Private equity returns now have to be earned in operations
private-equity-returns-from-operations
Article
Laura Kemper and Trevor Ofori
With multiples flat and debt expensive, buyout returns depend on improving the companies themselves. Most value creation plans are not built for that.
The grid connection queue is now the real cost of the energy transition
grid-connection-queue
Article
Darren Koh and Kamran Sadeghi
Capital and turbines are no longer the bottleneck for new generation. Waiting years for a connection is, and developers and utilities need to plan around it.
Capital Projects 2026: why large projects overrun and what the best owners do first
capital-projects-2026
Report
Kamran Sadeghi and Patrick Hofer
A study of 212 energy and industrial projects above $250 million, how far they ran over budget and schedule, and the decisions before final investment that made the difference.
Finding hospital capacity without building new beds
hospital-capacity-without-new-beds
Article
Nathalie Phan and Gabriela Quintero
Most hospitals short of beds are short of discharges. Fixing the flow out of the hospital releases more capacity, faster and more cheaply, than a new wing.
Capital allocation when money costs something again
capital-allocation-when-money-costs-something
Article
Victor Amaral and Laura Kemper
A decade of cheap debt let weak investments hide inside strong balance sheets. With hurdle rates back above 9 percent, the capital budget needs a different process.