Capital Projects 2026: why large projects overrun and what the best owners do first
A study of 212 energy and industrial projects above $250 million, how far they ran over budget and schedule, and the decisions before final investment that made the difference.


Kamran Sadeghi and Patrick Hofer
Share

Photo:
27%
median cost overrun on projects above $250 million
1 in 6
projects finished within 5 percent of the sanctioned budget and schedule
2.4x
larger overruns where design was less than 30 percent complete at sanction
Energy and industrial companies are about to spend more on large projects than at any time in the past two decades. Grid upgrades, low-carbon fuels, battery and semiconductor plants, and the replacement of ageing process units all require investments of hundreds of millions of dollars, often several at once. Most of these companies have a long record of building such projects late and over budget.
This report examines why. We collected cost and schedule data for 212 projects with a sanctioned budget above $250 million, completed between 2015 and 2025 by owners in Europe, North America and Asia-Pacific. For each, we compared the estimate at final investment decision with the outturn, and interviewed project directors and executive sponsors about the decisions that shaped the result.
The findings are sobering, but they are also specific. Most of the variation between good and poor outcomes is explained by a small number of choices made before the investment decision, when changing course is still cheap.
Key findings
Overruns are the norm. The median project finished 27 percent over its sanctioned budget and 9 months late. Only one in six landed within 5 percent of both budget and schedule.
Immature design is the largest single cause. Projects sanctioned with less than 30 percent of engineering complete overran by 2.4 times as much as those sanctioned at 60 percent or more.
Schedule pressure is expensive. Projects whose sanction date was brought forward to meet a market window or a subsidy deadline overran by 38 percent on average, against 19 percent for the rest.
Contract strategy matters less than expected. Lump-sum contracts did not protect owners from overruns on first-of-a-kind projects. Claims and change orders added an average of 16 percent to their cost.
Owner teams are thin. Owners spent on average 3 percent of project cost on their own team. Those that spent 5 to 7 percent had overruns less than half as large.
Independent review works when it can stop a project. Owners with a review gate that had delayed or rejected at least one project in the past five years saw a median overrun of 12 percent.
Methodology
Project data was gathered between October 2025 and February 2026 from 41 owner organizations in power generation, transmission, oil and gas, chemicals, metals and advanced manufacturing. Each project had a sanctioned budget above $250 million and reached mechanical completion between 2015 and 2025. Budgets and outturns were compared in constant 2025 dollars, adjusted for scope changes approved by the owner’s board.
The quantitative analysis was supplemented by 58 interviews with project directors, executive sponsors and heads of capital projects, and by a review of sanction documents for 30 of the projects. Results for individual owners are not disclosed.
Keep reading
Directors' briefing: overseeing AI without becoming the AI committee
board-ai-oversight-briefing
Event
Trevor Ofori and Patrick Hofer
A morning briefing in Zurich, also streamed online, for board members on the questions to ask about AI risk, regulation and return, and how to fit them into the board's calendar.
Software Pricing 2026: the move from seats to usage
software-pricing-2026
Report
Divya Raghavan and Darren Koh
A survey of 318 B2B software companies on how AI features are changing what they charge for, how customers respond, and which pricing models are holding up.
Separating a business cleanly: a roundtable on carve-outs
carve-outs-roundtable
Event
Kamran Sadeghi and Victor Amaral
A small morning session in London for executives preparing to sell or spin off a division, on stranded costs, transition services and keeping both businesses running.
What China-plus-one sourcing really costs consumer brands
china-plus-one-sourcing-costs
Article
Gabriela Quintero and Divya Raghavan
Moving production to a second country lowers tariff exposure but adds cost in places most business cases miss. Here is how to size it before committing.
Workforce planning in insurance: plan for skills, not headcount
workforce-planning-in-insurance
Article
Lucy Barlow
Insurers face a retirement wave in underwriting and claims just as automation changes the work. Planning by headcount misses both. Planning by skill family does not.
Private equity returns now have to be earned in operations
private-equity-returns-from-operations
Article
Laura Kemper and Trevor Ofori
With multiples flat and debt expensive, buyout returns depend on improving the companies themselves. Most value creation plans are not built for that.
The grid connection queue is now the real cost of the energy transition
grid-connection-queue
Article
Darren Koh and Kamran Sadeghi
Capital and turbines are no longer the bottleneck for new generation. Waiting years for a connection is, and developers and utilities need to plan around it.
Capital Projects 2026: why large projects overrun and what the best owners do first
capital-projects-2026
Report
Kamran Sadeghi and Patrick Hofer
A study of 212 energy and industrial projects above $250 million, how far they ran over budget and schedule, and the decisions before final investment that made the difference.
Finding hospital capacity without building new beds
hospital-capacity-without-new-beds
Article
Nathalie Phan and Gabriela Quintero
Most hospitals short of beds are short of discharges. Fixing the flow out of the hospital releases more capacity, faster and more cheaply, than a new wing.
Capital allocation when money costs something again
capital-allocation-when-money-costs-something
Article
Victor Amaral and Laura Kemper
A decade of cheap debt let weak investments hide inside strong balance sheets. With hurdle rates back above 9 percent, the capital budget needs a different process.